Project Development Process Exhibit

This exhibit is available in PDF format. If you do not have a copy of the Adobe PDF Reader, you can download one for free.

Due to the large size of this exhibit, you will need to "zoom in" to read the text. This can be accomplished by using the magnifying glass near the top of screen or by increasing the percentage near the bottom left. If you have any problems viewing this document, please contact the Webmaster.

Project Development Process Flow Chart (247 KB)Get the free PDF Viewer
This flowchart summarizes the process, which the Texas Department of Transportation follows to take a project from initial inception through construction.

The blocks on the left-hand side of the flowchart indicate major tasks in the project development process. The flowchart then breaks these tasks into steps that are required to bring a project to a stage ready for construction. The four stages of project development are listed along the top in white blocks.

Projects must be designated as Priority 1 projects for actual construction to begin. Projects designated as Priority 2 can be developed through the point of right-of-way acquisition, utility adjustment and contract plan preparation.

The legend at the bottom of the flowchart indicates by color where the Interstate Project Office was in the process at the time this display was presented in the initial round of public meetings.

This exhibit is based on a chart from the Project Development Process Manual. It is available in DynaWeb and PDF formats.